Defects liability period insurance: who pays after handover

The contract sends the builder back to fix defects for months after handover. The insurance that comes along is narrower than the cover that applied during the build.

By Vantage TeamPublished by Raphael Hermiz, Director, Qualified Insurance Broker7 min read

Six weeks after handover, an owner reports a damp patch below the new ensuite. The plumber opens the wall, finds a joint that was never sealed properly, and while cutting it out nicks the hot water line. Water runs through the new ceiling below, across the new timber floor and into the owner's lounge suite. The builder still has a contract works policy and a public liability policy on file, and the question is what either of them does now.

The answer depends on separating four costs that arrive on the same invoice: the bad joint, the damage the joint caused before anyone noticed, the damage the return visit caused, and the owner's own property. This article takes them in turn, using published Australian policy wordings. Your own wording, schedule and contract decide any actual claim.

When does full contract works cover stop?

Full cover usually stops at practical completion, or earlier if the owner starts using the building. A Vero contract works and legal liability wording dated May 2019 ends its construction period at the first of three events: practical completion, a separable portion being taken over or taken into use by the principal, or the expiry date on the schedule.

Two details in that wording matter. Practical completion is reached even though minor omissions and minor defects remain, so a live defects list does not keep the construction period open. And the separable portion limb means a staged handover can end full cover on one unit or one floor while the rest of the job is still being built. If the owner moves in before the paperwork is signed, the date the insurer uses may not be the date on the certificate.

What is covered in the defects liability period?

The cover that follows handover is maintenance period cover, and it is narrower. In the Vero wording, the loss or damage has to show itself during the maintenance period, and it has to originate from one of these:

  • A cause that arose during the construction period, at the contract site.
  • An act or omission of an insured person while on site complying with the defects liability or maintenance provisions of the contract.

The VMIA construction risks policy issued to Victorian government clients for November 2025 to October 2026 uses nearly the same two limbs, and so does the material damage policy for the NSW Project Remediate program. In the opening example, the floor and ceiling soaked by the nicked pipe would be assessed under the second limb, provided the plumber is an insured person under the policy and was there to meet the defects provisions of the contract.

What sits outside both limbs matters as much. If a storm damages the finished roof two months after handover, and the cause has nothing to do with the construction work or the builder's return, it does not readily fit either source. That loss generally belongs with the owner's building insurance.

Why is the defect itself not insured?

Fixing the defect is the cost of finishing the contract properly, and construction policies are written to exclude it. The Vero wording excludes the cost of repairing, replacing or rectifying any part of the works in which there is a fault, defect, error or omission in design, material or workmanship. It then pays for damage resulting directly from that fault, less what it would have cost to fix the faulty part had no damage occurred. In the example, the joint is the builder's cost. The ceiling it wet may be resulting damage, subject to the gradual deterioration exclusion.

The defects exclusion comes in more than one standard form. The VMIA and Project Remediate policies both set out two of them:

  • LEG 2/96 takes out the cost that would have been incurred if the defective portion had been replaced or rectified immediately before the damage happened.
  • LEG 3/06 takes out only the cost incurred to improve the original material, workmanship, design, plan or specification, once damage has occurred.

Both policies also state that property is not regarded as damaged solely because a defect exists in it. A wall built out of plumb, a membrane laid too thin or tiles set to the wrong fall are defects without damage, and there is nothing for the material damage section to respond to. For trades whose work is hidden behind a finish, such as waterproofers and plumbers, this is the clause worth reading first.

Does public liability cover the return visit?

Liability cover is what responds to injury, and to damage to property that is not part of your works. The lounge suite in the example is that kind of loss: it belongs to the owner and was never part of the contract. The construction liability policy arranged by Main Roads Western Australia covers liability for injury and property damage happening during the construction period or the defects liability period, which is the point to confirm on any project liability section.

The building you handed over is harder. The liability section of the Vero wording excludes damage to property that consists of or forms part of the contract works, leaving that damage to the maintenance cover in the other section. The Main Roads WA policy excludes the cost of making good defective workmanship, but limits that exclusion to the part that is defective and does not apply it to other parts of the works damaged as a consequence. The same wet ceiling can therefore be treated differently under two policies.

A trade that carries a standalone annual public liability policy and no contract works cover has a different set of questions: whether completed work is covered, how the faulty workmanship exclusion is worded, and whether conditions such as hot work procedures apply on a return visit.

How long does the cover need to run?

Long enough to match the defects liability period in the contract, because the policy will not necessarily stretch to fit it. Consumer Affairs Victoria describes the clause in a domestic building contract as giving the builder three, six or nine months. Procore's guide for Australian contractors puts the usual range at 6 to 24 months, with 12 the most common. The Project Remediate policy, for one, says the period shall not exceed the one stated in its schedule, which is 12 months initially.

Some contracts restart the clock on work that has been rectified. The Project Remediate policy allows its period to extend for that rectified work, up to the length of the original period. The Main Roads WA liability policy allows up to 24 months after the rectification is complete. A policy with no such clause can leave a renewed contractual obligation running past the insured period.

Statutory timeframes are a separate obligation and can run much longer. In NSW, Building Commission NSW gives the statutory warranty periods as six years from completion for major defects and two years for all others. In Queensland, the QBCC says it has six years and six months from completion to direct a contractor to rectify structural defects, while a complaint about non-structural defects must reach it within 12 months of completion. Maintenance period cover is not designed to follow a builder through those years.

Run-off or transfer: how annual policies differ

If you hold an annual contract works policy, the basis it is written on decides whether a job handed over last year is still insured this year. The Vero wording offers both versions as endorsements.

  • Run-off basis: the policy attaches to works that commence between the policy dates. Cover for those works continues until their maintenance periods expire, even if the policy is cancelled or not renewed, subject to any additional premium.
  • Transfer basis: the loss, damage or injury has to occur between the policy dates, so the maintenance period of an older job depends on a policy being in force when the damage happens.

The risk appears when a builder changes insurer. Moving from a transfer policy to a run-off one can leave jobs already under way, or recently handed over, outside both: the old policy has ended, and the new one only picks up works that start after it begins. The endorsements also cap the length of the maintenance period for each job, so a contract with an unusually long defects clause is worth declaring before the work starts.

A defects list keeps the contract open. It does not keep the construction period open.

Where the uninsured costs go

The cost of the defect stays with whoever is responsible for it, so the useful work is in deciding who that is. Several other arrangements may be relevant, and none of them is a substitute for contract works cover:

  • A subcontractor whose work was defective may be obliged under the subcontract to return and fix it. That is a contractual recovery, and the subcontractor's liability policy is likely to exclude the same rectification cost.
  • A defect that began as a design error raises a different policy. The Vero liability section excludes breach of a professional duty. Builders who take on design, and the engineers they engage, generally look to professional indemnity for that exposure.
  • Home building compensation cover in NSW exists for the consumer. Building Commission NSW says it allows a claim for loss from defective or incomplete work if the contractor becomes insolvent, dies or disappears. It does not fund a trading builder's own rectification work.
  • Consequential loss, penalties and liquidated damages are excluded by the Vero material damage section, as is wear and tear.

What to check before handover

Handover is the last convenient time to find a gap. These are the points Vantage works through when it reads a builder's contract against the policy schedule:

  • The defects liability period in the contract, and the maintenance period on the schedule, in months.
  • Whether the contract restarts the period for rectified work, and whether the policy follows.
  • Which defects exclusion applies, and whether a different one is available.
  • Whether an annual policy is written on a run-off or transfer basis, and what happens to open jobs at renewal.
  • Whether the liability cover extends to completed work once all obligations under the contract have ended. In the Vero wording that is a separate endorsement for builders.
  • Whether the subcontractors coming back hold current liability cover on the date they return, not only on the date they first started.
  • Whether the owner has building insurance in force from the day they take over.

If the two periods do not match, raise it with the insurer before handover rather than after a loss. The builder insurance page covers the wider program, and a tradie insurance review can put the contract and the schedule side by side before the keys change hands.

Filed under

Business

All insights

A conversation over an article?

Bring the specifics — we'll bring the cover.

Every business is different. If something in this article raised a question about your own cover, the fastest way to answer it is a short call.